经验教训:美国火星探测器1999年在火星坠毁的事故调查报告

[复制链接]

403

主题

575

帖子

2154

积分

论坛元老

Rank: 7Rank: 7Rank: 7

积分
2154
发表于 2019-2-7 23:04:48 | 显示全部楼层 |阅读模式


MCO,1999年,因为单位制的错误,导致参数设定出现了问题
回复

使用道具 举报

403

主题

575

帖子

2154

积分

论坛元老

Rank: 7Rank: 7Rank: 7

积分
2154
 楼主| 发表于 2019-2-7 23:05:39 | 显示全部楼层
Douglas Isbell/Don SavageHeadquarters, Washington, DC                    Nov. 10, 1999(Phone:  202/358-1547)             Embargoed until 2 p.m. ESTRELEASE:  99-134
MARS CLIMATE ORBITER FAILURE BOARD RELEASES REPORT, NUMEROUS NASA ACTIONS UNDERWAY IN RESPONSE
Wide-ranging managerial and technical actions are underway at NASA's Jet Propulsion Laboratory, Pasadena, CA, in response to the loss of the Mars Climate Orbiter and the initial findings of the mission failure investigation board, whose first report was released today.
Focused on the upcoming landing of NASA's Mars Polar Lander, these actions include: a newly assigned senior management leader, freshly reviewed and augmented work plans, detailed fault tree analyses for pending mission events, daily telecons to evaluate technical progress and plan work yet to be done, increased availability of the Deep Space Network for communications with the spacecraft, and independent peer review of all operational and contingency procedures.
The board recognizes that mistakes occur on spacecraft projects, the report said. However, sufficient processes are usually in place on projects to catch these mistakes before they become critical to mission success. Unfortunately for MCO, the root cause was not caught by the processes in place in the MCO project.
"We have mobilized the very best talent at the Jet Propulsion Laboratory (JPL) to respond thoroughly to the specific recommendations in the board's report and the other areas of concern highlighted by the board," said Dr. Edward Stone, director of JPL. "Special attention is being directed at navigation and propulsion issues, and a fully independent 'red team' will review and approve the closure of all subsequent actions. We are committed to doing whatever it takes to maximize the prospects for a successful landing on Mars on Dec. 3."
The failure board's first report identifies eight contributing factors that led directly or indirectly to the loss of the spacecraft. These contributing causes include inadequate consideration of the entire mission and its post-launch operation as a total system, inconsistent communications and training within the project, and lack of complete end-to-end verification of navigation software and related computer models.
"The 'root cause' of the loss of the spacecraft was the failed translation of English units into metric units in a segment of ground-based, navigation-related mission software, as NASA has previously announced," said Arthur Stephenson, chairman of the Mars Climate Orbiter Mission Failure Investigation Board. "The failure review board has identified other significant factors that allowed this error to be born, and then let it linger and propagate to the point where it resulted in a major error in our understanding of the spacecraft's path as it approached Mars.
"Based on these findings, we have communicated a range of recommendations and associated observations to the team planning the landing of the Polar Lander, and the team has given these recommendations some serious attention," said Stephenson, director of NASA's Marshall Space Flight Center, Huntsville, AL.
The board's report cites the following contributing factors:

  • errors went undetected within ground-based computer models of how small thruster firings on the spacecraft were predicted and then carried out on the spacecraft during its interplanetary trip to Mars
  • the operational navigation team was not fully informed on the details of the way that Mars Climate Orbiter was pointed in space, as compared to the earlier Mars Global Surveyor mission
  • a final, optional engine firing to raise the spacecraft's path relative to Mars before its arrival was considered but not performed for several interdependent reasons
  • the systems engineering function within the project that is supposed to track and double-check all interconnected aspects of the mission was not robust enough, exacerbated by the first-time handover of a Mars-bound spacecraft from a group that constructed it and launched it to a new, multi-mission operations team
  • some communications channels among project engineering groups were too informal
  • the small mission navigation team was oversubscribed and its work did not receive peer review by independent experts
  • personnel were not trained sufficiently in areas such as the relationship between the operation of the mission and its detailed navigational characteristics, or the process of filing formal anomaly reports
  • the process to verify and validate certain engineering requirements and technical interfaces between some project groups, and between the project and its prime mission contractor, was inadequate
The failure board will now proceed with its work on a second report due by Feb. 1, 2000, which will address broader lessons learned and recommendations to improve NASA processes to reduce the probability of similar incidents in the future.
Mars Climate Orbiter and its sister mission, the Mars Polar Lander, are part of a series of missions in a long-term program of Mars exploration managed by the Jet Propulsion Laboratory for NASA's Office of Space Science, Washington, DC. JPL's industrial partner is Lockheed Martin Astronautics, Denver, CO. JPL is a division of the California Institute of Technology, Pasadena, CA.
The Board's report is available on-line at:
Charts used in the briefing today are available on-line at:

回复 支持 反对

使用道具 举报

您需要登录后才可以回帖 登录 | 立即注册

本版积分规则

QQ|京ICP备17005959号|IAC-16|Archiver|手机版|小黑屋|CCOSE论坛

GMT+8, 2019-11-20 16:51 , Processed in 1.206813 second(s), 20 queries .

Powered by Discuz! X3.4

© 2001-2017 Comsenz Inc.

快速回复 返回顶部 返回列表